Prep work is continuing with efforts being focusing on getting James and the houses along College Street and Railroad Avenue ready for demolition. College employees recently received the following e-mail:

Dear Campus Community,

Starting on the week of May 22nd - demolition work in association with
the New Science Building will commence, and will continue until
completion, in July.

In the interest of sustainability and in a large effort to re-use and
recycle building materials and to reduce the amount of demolition waste
that goes to the landfill, we are salvaging materials and fixtures out
of the buildings that will be demolished. The demolition contractor
will salvage many of the materials as part of their contract with the
College, and the Old Neighborhood League of Carlisle has also been given
salvage permission for materials and fixtures with historic
significance. Other salvageable materials and fixtures will be made
available to the College community on a "First-Contact First-Get" basis.
If you're interested, please read on.

Buildings Being Demolished:
James Hall
The Railroad Avenue Houses (5 of them)
136 N. College Street
140/142 N. College Street
150 N. College Street


Materials With Salvage Potential:
Windows
Doors
Ceiling Tiles
Miscellaneous Built-in Cabinetry
Miscellaneous Plumbing and Electrical Fixtures
Miscellaneous Appliances


Materials NOT AVAILABLE for Salvage:
Structural System Components
Wiring
Piping

Salvage Process:

* Frank Laquitara is managing the demolition process - including
the salvage process.
* Contact Frank if you are interested in salvaging building
materials or fixtures - email = laquitar@dickinon.edu .
* Salvage approval will occur on a "First-Contact First-Get"
basis, which will be tracked by Frank.
* You must schedule your salvage activity with Frank.
* You must sign a liability waiver prior to salvage activity or
receiving salvaged materials or fixtures.


Salvage Schedule:

* Railroad Houses: May 18, 19, 20.
* North College Street Houses: May 29, 30, 31
* James Hall: June 7,8,9 & 12,13